The City of Great Falls has a contract with Capcon Inc. for the storm drain, water main, and street improvements in the downtown area along 1st Ave S from 3rd St S to 5th St S and along 3rd St S from Central Ave to 2nd Ave S. To minimize disruption, the project will be constructed in sections. Beginning Monday, June 2nd, 3rd St S will be closed from 1st Ave S to 2nd Ave S to replace storm drain. To assure no conflicts related to the 4th of July parade, construction along 1st Ave S will not begin until after July 4th.
Capcon, Inc. will provide barricades and detour signs for traffic routing. For more information, please contact Matt Proud, Civil Engineer Sr., City of Great Falls, at (406)771-1258 or Bryan Guckeen with Capcon, Inc. at (406)899-1039.